Friday, December 12, 2025

The Engine Delay Euphemism: HAL’s Go-To Explanation for Missed Deadlines

 


The HT, quoting PTI, reported on December 12, 2025, that HAL has revised the delivery schedule for the LCA Mk-1A and HTT-40. It now aims to deliver 5 LCA Mk-1A jets and 3 HTT-40 trainers by March 2026.

HAL had earlier committed to deliver 10 LCA Mk-1A fighters and 12 HTT-40 trainers by March 2026.

HAL attributes the timeline revision for the LCA Mk-1A to delays in the completion of weapons trials and the delivery of GE F404 engines, and for the HTT-40 to delays in delivery of the Honeywell TPE331-12B turboprop engine.

LCA Mk-1A Orders

A total of 180 Tejas Mk-1A fighters are on order with HAL — 83 against an initial order placed in February 2021 and 97 under a follow-up order placed in September 2025.

HAL has created three production lines for the aircraft.

GE-F404-IN20 Delivery

Based on the initial LCA Mk-1A order, HAL placed an order for 99 GE F404 engines with General Electric (GE) Aerospace on August 17, 2021.

Ironically, when HAL placed this order, GE Aerospace had already shut down the F404-IN20 production line after fulfilling prior commitments by delivering 65 engines for the Tejas LCA by 2016, with no further orders anticipated at that time.

HAL’s August 2021 order for an additional 99 engines required reactivation of the dormant line and vendor supply chain after a five-year hiatus. The reactivation faced further challenges because of the COVID-19 pandemic. As a result, there was a significant delay, and the first engine arrived only in March 2025.

Having resumed production in 2024, GE is now producing just a few F404 engines per month.

HAL likes to attribute LCA Mk-1A delivery timeline slippages entirely to “supply chain constraints” in the production of GE F404 engines. In reality, the slippages are largely attributable to delays in developing the Tejas Mk-1A, which led to the shutdown of the GE F404 production line. The truth is, HAL is still not ready to deliver LCA Mk-1A aircraft because of pending weapons trials.

Additional Order

The MoD, on September 26, 2025, signed a ₹62,370 crore contract with HAL for the procurement of 97 LCA Mk-1A aircraft for the Indian Air Force (IAF), including 68 fighters and 29 twin-seaters, along with associated equipment.

Delivery of these aircraft will commence during 2027–28 and be completed over a period of six years. The aircraft will have an indigenous content of over 64%, with 67 additional items incorporated over and above the previous LCA Mk-1A contract.

To fulfil the additional order, HAL announced on November 7, 2025, that it had signed a deal with GE Aerospace for 113 F404-IN20 engines. The deal, estimated to be worth $1 billion, includes a support package for execution of the programme.

The engine deliveries will take place between 2027 and 2032, HAL said in a statement on X.

According to the HT report, HAL is confident of making good on the timeline slippages in the years ahead.



HTT-40 Orders

During DefExpo 2022, HAL and the IAF signed an agreement for the supply of 70 HTT-40 trainers to the IAF for basic training.

The Ministry of Defence, on March 7, 2023, signed a contract with HAL for the supply of 70 HTT-40 Basic Trainer Aircraft.

Reportedly, HAL was to deliver the first trainer by September 2025 and a total of 12 trainers by March 2026. Supply of all 70 aircraft on order was to be completed over a period of six years.

TPE331-12B Engines

In July 2022, HAL signed a $100 million contract with Honeywell for 88 engines to power the HTT-40. Under the contract, Honeywell would deliver 32 engines, with the rest to be built at HAL through technology transfer.

Notably, HAL placed the order on Honeywell based on its DefExpo 2022 agreement with the IAF, without waiting for a formal contract from the MoD.

According to the HT report, the first engine is expected to arrive in January 2026, another four by March 31, and the rest at the rate of two per month.

HT also reports that two series-production HTT-40s are already flying with “Category B” (used) TPE331-12B engines, earlier fitted on prototype aircraft.

Copyright © Vijainder K Thakur. First published on Thumkar.

Wednesday, December 21, 2016

HAL Mk-1A AESA Radar RFQ Details


Tejas LCA Mk-1 at Aero India 2015

On December 14, 2016 HAL (ARDC) released a Request For Quotation (RFQ) for Supply of AESA Radar for Light Combat Aircraft (LCA Mk1A) Program. 

The RFQ was limited to the following vendors

  1. Elta Systems, israel 
  2. Saab, Sweden 
  3. Raytheon, USA 
  4. Thales, France 
  5. Rosoboronexport, Russia 



 ARDC wants an  AESA Radar that can be integrated with other onboard avionics of the LCA, its EW suite comprising Digital RWR and podded jammer, combined interrogator & transponder (CIT), short range air to air missiles and BVR missiles. 

 The AESA must be supplied with a compatible Radome.

The selected vendor is to 

  1. Supply a contemporary AESA Radar along with technical support for integration, ground/flight testing and certification. 
  2. Supply 3 aircraft sets of Radar for Trial Modification and certification phase and subsequently against anticipated orders for 80 aircraft sets for series production. 
  3. Enter into a ToT for Repair/overhaul/servicing of AESA Radar and connected items by HAL at its facilities under a Transfer of Technology (TOT) agreement aat the appropriate stage. 
  4. Provide supplies and services needed for product support to HAL’s customers. 


The supply contract would be implemented in phases as follows
  1. Trial Modification & Certification Phase 
  2. Series Production Phase: 



Trial Modification & Certification Phase 

HAL will release purchase order for 3 aircraft sets of Radar system.  SOF testing should be completed on the three aircraft sets before delivery.  

HAL will arrange for two aircraft to be used for trial modification, Integration, flight testing and certification. 

Series Production Phase

 It is estimated that a total of 80 AESA Radar system sets would be required. Series production is expected to commence from year 2019. The production of Radar systems is planned to be executed in a phased manner as follows. 

Phase-0: Direct purchase of 24 Radar system sets in fully formed condition. 
Phase-1: Manufacture of 08 Radar system sets by HAL based on Semi Knocked Down (SKD) kits to be supplied by the vendor. 
Phase-2: Manufacture of 48 Radar system sets by HAL based on transfer of technology to HAL by the vendor. 

During series production programme, Purchase orders are planned to be placed for annual requirement depending upon the number of aircraft to be produced in each year based on customer orders.  Issue of this RFQ does not create any obligation whatsoever on HAL to place orders for series production.  

Platform Integration

 Vendor shall be responsible for integration of the AESA radar with LCA Mk1A platform and avionics systems.

Vendor shall be responsible for Design and Development of a compatible Radome conforming to the established outer mold line (OML) specifications for the LCA Mk1A and tailored to optimize operational performance of the AESA radar. 

Vendor shall be responsible for integration of the AESA Radar with EW suite consisting of Digital RWR and podded Jammer on LCA Mk1A platform as per LCA Mk1A requirements, in coordination with the Vendor of EW Suite to ensure interoperability of Radar, EW suite and other avionics system.   
Vendor shall be responsible for integration of AESA radar with Indian IFF interrogator/ Transponder (CIT) as per LCA Mk1A requirements. 

Vendor shall be responsible for integration of AESA radar with third party BVR missile as per LCA Mk1A requirements. 

IPR   

 HAL shall have exclusive worldwide sale and product support rights for the LCA MK1A aircraft or its variants fitted with the Radar system being developed specifically for LCA Mk1A programme through the present RFQ. HAL shall also have the right to use the Radar system or its adapted versions on any other airborne platform designed or produced by HAL for use by Indian defence customers.  

IPR held by the vendor or his suppliers shall not in any way restrict or hamper by way of quantity or otherwise manufacturing of the Radar system by HAL under TOT-MFG or Repair & Overhaul by HAL under ToT-ROH. 

The vendor shall not sell the Radar system being developed through this RFQ to any other customers or transfer the IPR of the system to any third party without prior written consent by HAL. 

This clause shall continue to be in force for an indefinite period even after fulfillment of all activities and obligations covered under this RFQ. 

LCA Mk-1A EW Suite Details

Tejas LCA Mk-1 at Aero India 2015

On December 15, 2016 HAL's Aircraft Research & Design Centre (ARDC) invited Request For Quotation (RFQ) for Supply of EW Suite for Light Combat Aircraft (LCA Mk1A) Program.

The EW Suite would comprise of a digital RWR and podded jammer.

The following vendors were invited to quote.

  1. Elbit systems, Israel 
  2. Elta systems, Israel 
  3. Saab, Sweden 
  4. Thales, France 
  5. Elettronica s.p.a, Italy 
  6. Raytheon, USA
  7. Indra systems, Spain 

Notably, no Russian company has been invited to bid for the project.

ARDC wants an EW Suite that can be integrated with other onboard avionics of LCA, including its AESA Radar and CMDS. 

The RFQ is aimed at selecting a vendor for the supply of contemporary EW Suite  including technical support for integration, ground/flight testing and certification. 

HAL wants the selected vendor to supply 3 EW Suite for Trial Modification and certification phase and subsequently against anticipated orders for 80 aircraft sets for series production. 

ToT

The selected vendor would need to enter into a ToT agreement at the appropriate time to enable HAL to undertake repair/and overhaul (ROH) / servicing of EW Suite and connected items at its facilities. 

The selected vendor would need to enter into a ToT agreement to facilitate HAL to undertake phased manufacture of EW Suite systems at the appropriate stage. 

Vendors would need to provide supplies and services needed for product support to HAL’s customers. 

Order Quantity

Currently, there is an anticipated requirement for 80 EW Suite sets. Series production of LCA Mk-1A is expected to commence from year 2019. The production of EW Suite is planned to be executed in a phased manner as follows. 

Phase-0: Direct purchase of 24 EW Suite sets in fully formed condition. 
Phase-1: Manufacture of 08 EW Suite sets by HAL based on Semi Knocked Down (SKD) kits to be supplied by the vendor.  
Phase-2: Manufacture of 48 EW Suite sets by HAL based on transfer of technology to HAL by the vendor. 

IPR

HAL shall have exclusive worldwide sale and product support rights for the LCA Mk-1A aircraft or its variants fitted with the EW Suite being developed specifically for LCA Mk-1A program through the present RFQ. HAL shall also have the right to use the EW Suite or its adapted versions on any other airborne platform designed or produced by HAL for use by Indian defense customers.  

IPR held by the vendor or his suppliers shall not in any way restrict or hamper by way of quantity or otherwise manufacturing of the EW Suite by HAL under ToT-MFG or Repair & Overhaul by HAL under ToT-ROH. 

The vendor shall not sell the EW Suite being developed through this RFQ to any other customers or transfer the IPR of the system to any third party without prior written consent by HAL. 

This clause shall continue to be in force for an indefinite period even after fulfillment of all activities and obligations covered under this RFQ. 

Vendors are required to submit price quotations before February 15, 2017 and the final selection will be made before April 2017.